    In July Tutt Bryant Project Services (TBPS) executed the movement of a large
    Naphtha Column which weighed just over 286 T. The Column was supported by
    two large platform trailers with turn tables which were required to
    distribute weight of the load and allow the Column to be manoeuvred safely
    along the route. The overall weight of the combination exceeded 500 T and
    required 3 x heavy duty prime movers to complete the haul. The move
    commenced at daylight on Sunday and took approx 4 hours to travel 4kms due
    to the heavy electrical line switching programme. TBPS team worked very
    closely with the local shire, WA Main Roads and Western Power to ensure the
    move was successfully executed.





































     